Emission cuts realities for electricity generation – costs and CO2 emissions

We must cut our carbon emissions immediately!“… “We have to transition rapidly to 100% renewable energy!“… “A massive nuclear build out is the only logical course of action!“… and so on. We get these well-meant but hand-waving arguments all the time, almost always bereft of real-world numbers — especially those with $$ attached. This greatly limits their utility and credibility. Without a practical, pragmatic plan, we aren’t going to get anywhere and the people in control of the purse strings will not pay them serious attention.

That’s why I’m so happy to present this new, clear-headed analysis by Peter Lang on BraveNewClimate (which was spawned by in the discussion threads of previous posts on wind and solar power — their costs and ability to mitigate carbon emissions). Using Australia as a case study (although the same principles would apply in almost any developed economy that is currently reliant on fossil fuel energy), Peter considers six electricity supply scenarios for the period 2010 to 2050 — a high-carbon business-as-usual projection as a reference, and five low(er) carbon alternatives. In each of the alternatives, coal-fired power stations are retired, and not replaced, such that by the period 2035 — 2040, the last few are closed.

These analysis are simple, clearly presented and easily understood. Yet they’re also realistic in the same way that David Mackay’s energy plans are realistic — they add up (although Mackay was concerned about whether the physics are right, Lang is concerned about whether the $$ and build rates are plausible). They are an apples and apples set of plans, in the sense that they represent reasonable relative comparisons which all aim to achieve the same goal, in different ways. Like any modelling exercise, the uncertainties lie in the quality of the input data and the acceptability of the assumptions made. Peter makes them quite explicit. If you wish to disagree and propose/source your own numbers, fine, but remember that the onus is then on you to justify your assumptions.

I’ll stop and this point and let you read the analysis. Get yourself a large mug of coffee or a tall glass of wine, and settle in for an interesting read. After that, let the comments fly. I certainly have my own points to make about where I think the analysis is most/least plausible, but that can come a little later…

——————————————————————

Emission Cuts Realities – Electricity Generation

Cost and CO2 emissions projections for different electricity generation options for Australia to 2050

By Peter Lang, January 2010

(Download the printable 32-page PDF version here, which also includes references and Appendices).

Peter Lang is a retired geologist and engineer with 40 years experience on a wide range of energy projects throughout the world, including managing energy R&D and providing policy advice for government and opposition. His experience includes: coal, oil, gas, hydro, geothermal, nuclear power plants, nuclear waste disposal, and a wide range of energy end use management projects.

Abstract

Five options for cutting CO2 emissions from electricity generation in Australia are compared with a ‘Business as Usual’ option over the period 2010 to 2050. The six options comprise combinations of coal, gas, nuclear, wind and solar thermal technologies.

The conclusions: The nuclear option reduces CO2 emissions the most, is the only option that can be built quickly enough to make the deep emissions cuts required, and is the least cost of the options that can cut emissions sustainably. Solar thermal and wind power are the highest cost of the options considered. The cost of avoiding emissions is lowest with nuclear and highest with solar and wind power.

Introduction

This paper presents a simple analysis of CO2 emissions, capital expenditure, electricity generation costs and the emissions avoidance cost for six options for supplying Australia’s electricity. The results are presented at five year intervals for the period 2010 to 2050.

The purpose of this paper is to address two questions that were raised in discussion of three earlier papers (Lang 2009a, Lang 2009b, Lang 2009c). The papers ‘Solar Power Realities’ (Lang 2009b), and the Addendum (2009c), looked at the cost of reducing CO2 emissions using solar power. They did this by looking at the limit situation; that is, we replace all our fossil fuel electricity generation ‘overnight’ with either solar power and energy storage or with nuclear power. The papers concluded that solar power would cost at least 40 times more than nuclear to supply the National Electricity Market (NEM). The estimates were based on current prices for currently available technologies and for the NEM demand in 2007.

The first paper, “Cost and Quantity of Greenhouse Gas Emissions Avoided by Wind Generation” (Lang 2009a), concluded that wind power with back-up by gas generators saves little greenhouse gas emissions and the avoidance cost is high compared with other alternatives.

Discussion of these analyses raised two main questions:

1. The limit situation does not take into account what happens during the transition period. The earliest we could begin commissioning nuclear is about 2020. So, what should we do until then? Does it make sense to build wind power as fast as possible until 2020, at least, so we can cut greenhouse gas emissions as quickly as possible and start as early as possible?

2. The previous papers consider replacement of fossil fuel generators with one technology only rather than with a mix of technologies. This raises the question: would a mix of technologies be better able to meet the demand and at lower cost. Would a mix of solar and wind be lower cost than either alone, and lower cost than nuclear?

To attempt to answer these questions, in a ‘ball park’ way, I conducted a simple analysis of the cost, and CO2 emissions from six options (six technology mixes) for the period 2010 to 2050. The six options are:

1. Business as Usual (BAU).

2. Combined Cycle Gas Turbine (CCGT).

3. Nuclear and CCGT.

4. Wind and Gas [Gas means a mix of Open Cycle Gas Turbine (OCGT) and Combined Cycle Gas Turbine (CCGT)].

5. Solar Thermal and CCGT

6. Solar Thermal, Wind and Gas.

Throughout the paper ‘emissions’ refers to ‘CO2-e emissions’. More specifically, it refers to CO2-e emissions from electricity sent out from the power station. The figures are not life cycle emissions (see assumption 10, below).

Assumptions

Assumptions that apply to all options are described in this section. Assumptions that are specific to an option or to a technology are described under the relevant option in the Methodology section.

1. The total energy supplied is as per the ABARE (2007) projections of electricity supply to 2030, extended linearly to 2050. All options must supply this total energy for each period and all must provide the same quality of power as the Business as Usual case. To achieve this, intermittent renewable energy generators must be backed up by a responsive generator technology.

2. For all except the Business as Usual case, it is assumed that coal fired power stations can be and will be decommissioned at the rate of 1 GW per year for black coal generators and 0.4 GW per year for brown coal generators.

3. The energy deficit caused by decommissioning the coal fired power stations is supplied by replacement generating capacity. Five options for replacement generating capacity are considered. Each option comprises a mix of a few technologies that in combination are capable, theoretically, of providing the energy and the power that would have been provided by the coal power stations. That is, the mixes of replacement technologies must be capable of providing the same power quality, and of supplying it on demand, at all times.

4. The ABARE (2007) projections provide the breakdown of energy supply by nine generation types; four fossil fuel and five renewable energy. The energy supplied by the seven non-coal technologies is the same in all six options [There is one exception to this statement – see Option 3 – Nuclear and CCGT]. The Business as Usual case is as per the ABARE (2007) projections for all nine technologies.

5. The main constraint in the analyses is the assumed decommissioning rate for coal fired power stations and the assumed build rate achievable for the replacement technologies. The build rate assumptions are arguably optimistic. The achievability of the assumed build rates is discussed in a later section.

6. The capital expenditures do not include the cost of replacement of the reserve capacity margin that is needed to cover for scheduled and unscheduled outages because the reserve capacity margin is assumed to be the same for all options.

7. The analyses are intentionally simple so that non-specialists can follow the assumptions and analyses. A more thorough analysis would use sophisticated modelling to optimise the mix of technologies and to calculate the long run marginal cost of electricity sent out. All available technologies would be included in the analyses rather then the simple mixes used in these analyses. Such analyses are complicated and need sophisticated modelling capability. For examples see EPRI (2009a), MIT (2007), MIT (2009), ACIL-Tasman (2009), Frontier Economics (2009), ATSE (2008).

8. Transmission costs are similar for the Business as Usual, CCGT and Nuclear options. So no additional cost is included for transmission for the CCGT and Nuclear options. Extra costs for transmission are included for the Wind and Solar Thermal options.

9. No allowance is made for the lower energy growth rate that energy efficiency improvements will bring. This omission is offset because no allowance is made for the higher growth rate as cleaner electricity replaces gas for heating and replaces oil for land transport (either in electric vehicles or through synthetic fuels such as methanol or hydrogen that use electricity for their production).

10. CO2 emissions from nuclear and the renewable energy technologies are assumed to be zero in operation, consistent with DCC (2009), EPRI (2009b) and Frontier (2009). On a Life Cycle Analysis (LCA) basis the emissions from these technologies are small compared with fossil fuel generation. These are ignored in this simple analysis. [Lightbucket (2009) lists the results from authoritative studies of LCA emissions from electricity generation].

11. No attempt has been made to reconcile CO2 emissions calculated for the Business as Usual option with the emissions projections published by the Department of Climate Change (2009).

12. The ABARE (2007) energy projections are for all Australia’s electricity supply, both off-grid and on-grid. However, the analyses here apply the ABARE (2007) figures as if they were for grid connected electricity. This simplification means the potential for emissions reductions and the cost of the options is overstated (perhaps by 10% in early years decreasing over time).

Table 1 lists the CO2-e emissions intensities for sent out electricity in 2010 for the Business as Usual technologies.

Table 2 summarises the assumptions and inputs for the coal and replacement technologies.

Methodology

This section explains how the analyses were done.

Option 1 – Business as Usual (BAU)

The ABARE (2007) projections for electricity supply for the years 2005-06 to 2029-30 were extended to 2050 and converted from petajoules (PJ) to terawatt-hours (TWh). Figure 1 shows the energy projections for the Business as Usual option.

The CO2 emissions were calculated for the Business as Usual case by multiplying the energy by the CO2 emissions factors. The assumed emissions factors for 2010 are listed in Table 1. Emissions factors for the periods after 2010 were reduced at the rate of 1% per 5 years to account for average efficiency improvements for the existing generators and new generators. The renewable and nuclear technologies are assumed to produce zero emissions (Table 1).

To compare the cost difference between the options we need only compare the cost of the coal with the replacement technologies. All the other technologies are the same for all options.

The capital expenditure for coal in the Business as Usual case comprises two components:

a) the capital expenditure of new coal capacity added to meet the rising demand for electricity; and

b) the capital expenditure of new coal to replace old coal that has reached the end of its economic life. To work with capital expenditure, we must convert the energy figures in the ABARE projections to average power.

The energy (TWh) was converted to average power (GW) using a capacity factor of 90% (refer Table 2). As mentioned previously, this simple analysis ignores the reserve capacity margin needed in the generation system.

The amount of new coal capacity required each year for the Business as Usual case was calculated from the ABARE (2007) projections. The amount of new coal to replace existing coal at the end of its economic life was calculated as 2% of existing capacity per year [Assuming a 40 year economic life, the plants would be replaced at the rate of 2.5% per year if the capacity was constant from year to year. However, the capacity is increasing over time. In any one year we need to replace only the plants that are 40 years old. If the capacity doubles in 40 years, then we need to replace 1.25% of the total existing capacity in each year. I have assumed 2% as a round figure in between 1.25% and 2.5%.].

The capital cost of new coal capacity for the Business as Usual option was calculated by multiplying the amount of new coal capacity by the unit rate for Ultra Super Critical Black Coal (air cooled) and Ultra Super Critical Brown Coal (air cooled) (refer Table 35, ACIL-Tasman 2009).

All non-BAU options

For all options other than Business as Usual, black coal capacity is decommissioned at the rate of 1 GW per year, and brown coal at the rate of 0.4 GW per year. Decommissioning starts in 2010. All black coal is decommissioned by 2040 and all brown coal by 2035.

The amount of energy these power stations would have generated if not decommissioned is calculated. This is the energy deficit that must be supplied by the replacement generators in all the non Business as Usual options.

The CO2 emissions from the remaining coal capacity are calculated by multiplying the energy generated from black coal and brown coal by the emissions factor for that technology for that year.

The Business as Usual Option comprises projections for nine technologies, – Black Coal, Brown Coal and seven others. The emissions from all the seven non-coal technologies are the same for all options.

The following sections describe the five options considered here for replacing the energy from the decommissioned coal power stations.

Option 2 – Combined Cycle Gas Turbine (CCGT)

CCGT is built to replace the energy deficit resulting from the decommissioning of the coal fired plants. The amount of CCGT capacity required is calculated by multiplying the energy deficit by 90% capacity factor. Figure 2 shows the energy supplied by each technology.

The CO2 emissions for CCGT are calculated using a CO2 emissions factor of 0.45 t CO2/MWh, decreasing at 1% per five year to reflect increasing generation efficiency.

The CO2 emissions from the remaining coal generators and from the other seven technologies are included in the total for this option.

The capital cost for this option is calculated using the unit rate for new build CCGT (air cooled) given in Table 35, ACIL Tasman (2009), and decreasing at -0.4% pa from 2030 to 2050.

Option 3 – Nuclear and CCGT

For this option, nuclear power is commissioned at the rate of 1 GW per year from 2020 to 2025, then at 1.5 GW per year to 2030, then at 2 GW per year to 2050. The reason for selecting these rates is discussed below in “How achievable are the build rates”

CCGT is commissioned at the rate needed to make up the difference between the energy that the nuclear power can supply and the energy deficit caused by decommissioning the coal power stations. Figure 3 shows how much energy is produced by each technology.

From 2010 to 2019, no nuclear capacity is commissioned so the CCGT capacity is the same as in Option 2 – CCGT. From 2020 to 2025, nuclear is not built fast enough to replace the coal capacity being decommissioned, so CCGT is added to supply the energy deficit. After 2025, nuclear is being built faster than coal is being decommissioned. So, progressively less energy is being required from CCGT. This shows up (in this simple analysis) as a reduction in CCGT capacity. The practical interpretation of this is that the Natural Gas generation capacity would be reduced at this rate. This means that Natural Gas generation capacity would not be replaced at the end of its 30 year economic life. This begins from about 2025.

CO2 emissions for nuclear are assumed to be zero (see ‘Assumptions’ and Table 1). CO2 emissions for Coal, CCGT and the other technologies are calculated in the same way as for Option 2 – CCGT. As for capacity, the negative emissions shown against CCGT should actually be a reduction in emissions from ‘Natural Gas’ but for simplicity of calculation they are shown as negative for CCGT.

The capital cost calculations for this option are similar to those for Option 2 – CCGT. The cost of the nuclear capacity is at the unit rate in ACIL-Tasman (2009), Table 35, and decreasing at -0.9% pa from 2030 to 2035 then at -0.6% pa to 2050.

Option 4 – Wind and Gas

For this option, wind power capacity is commissioned at the same rate as the coal fired plants are decommissioned. So when all wind farms are producing full power (a rare event), the wind farms will supply all the energy that the decommissioned coal fired power plants would have supplied. When the wind farms are not producing full power, back-up generation is required to make up for the energy deficit.

Back-up capacity is provided by a combination of Combined Cycle Gas Turbines (CCGT) and Open Cycle Gas Turbines (OCGT). Equal proportions are assumed. A Capacity Credit of 8% is assumed (AER, 2009), so 1 GW of wind power capacity is assumed to be backed up by 0.46 GW of OCGT and 0.46 GW of CCGT [In practice more gas capacity will be built than this calculation indicates. OCGT and CCGT run at lower capacity factors in practice than the 90% used in this analysis for calculating the amount of capacity required]. The proportions, on the basis of capacity, are 1.0:0.46:0.46.

The energy is calculated assuming a capacity factor of 30% for Wind and availability of 90% for OCGT and CCGT. So, on average, 3 GWh of energy is supplied by a combination of Wind, OCGT and CCGT in the proportions 1:1:1. Figure 4 shows how much energy is produced by each technology.

CO2 emissions for wind generation are assumed to be zero (refer to ‘Assumptions’ and Table 1). The CO2 emissions for OCGT are calculated using a CO2 emissions intensity of 0.7 t CO2/MWh, decreasing at 1% per five years to reflect increasing generation efficiency. CO2 emissions for CCGT, Coal and the other technologies are calculated in the same way as for Option 2 – CCGT. The lower efficiency and higher emissions from the gas turbines when operating in back up mode (Lang, 2009a; Hawkins, 2009) are included in this analysis. The CO2 emissions are increased by 34% for OCGT and 17% for CCGT (Hawkins, 2009) when these technologies are operating in back-up mode. The higher emissions rate is applied to the proportion of the energy that is generated when they are assumed to be operating in ‘back-up’ mode. For simplicity this is assumed to be equal to the proportion of the replacement energy that is generated by Wind. In effect, the increased emissions factor is applied to half the energy generated by the CCGT and OCGT replacement generators.

The capital cost calculations for this option are similar to those for Option 2 – CCGT and Option 3 – Nuclear and CCGT. The capital cost of the wind capacity is $2591/kW (Average of seven wind farms listed as ‘under construction’ in ABARE (2009). This Australian cost is close to the US cost in EPRI (2009b), Table 7.1, p 7-5, which is US$2350/kW = A$2611/kW) in 2010 and decreasing in future periods at -0.6% pa (Frontier, 2009). The cost of OCGT and CCGT capacity is at the unit rate in ACIL-Tasman (2009), Table 35, increasing at +0.4% pa and +0.5% pa from 2030 to 2050.

As mentioned above, the OCGT and CCGT generators are less efficient when operating in back up mode for wind. These analyses assume that the electricity generation costs are 17% higher for CCGT and 34% higher for OCGT (Hawkins, 2009). However, only half the energy generated by these technologies is considered to be in back-up mode, so electricity cost is increased by 8.5% for CCGT and 17% for OCGT when operating in back-up mode.

Wind power is assumed to have an economic life of 25 years and gas 30 years. Wind and gas capacity installed in 2010 must be replaced in 2035 and 2040 respectively. The capital costs of replacing wind and gas at the end of their economic lives are calculated at the capital cost rate applicable for the year in which the replacement is commissioned.

Wind power requires significant additional capital expenditure for transmission and network management capability. Based on estimated costs for extra transmission capacity incurred because of wind generation in the USA, $1,000/kW of installed wind capacity is included (Gene Preston, pers. comm., 3 Nov 2009). The transmission cost for wind power raises the cost of electricity by an assumed $15/MWh on average (Gene Preston, Dec 2009, pers. comm. and EPRI, 2009a).

Option 5 – Solar Thermal and CCGT

This option is similar to Option 3 – Nuclear & CCGT but with solar thermal instead of nuclear.

The differences are:

1. The build rate of solar thermal capacity in this option (Option 5) is half the build rate of nuclear in Option 3 – Nuclear & CCGT

2. Therefore, the build rate of CCGT is higher in this option than in the Nuclear & CCGT option (to make up the energy difference). This means emissions are higher in the Solar & CCGT option than in the Nuclear & CCGT option.

3. Solar thermal capacity has an assumed life expectancy of 25 years so replacement of solar thermal capacity begins 25 years after the first installation; so replacement begins in 2045.

4. Whereas nuclear would be built near population centres, where work force, infrastructure, suppliers and services are available, this is not the case for solar thermal [The NEEDS (2009) costs are based on constructing the Andasol 1 solar thermal power station in Spain. The cost of constructing widely distributed solar thermal power stations over an area of some 3000 km by 1000 km in Australia’s deserts will be higher than the cost of constructing in Spain – where there is well developed infrastructure and larger work force nearer to the sites. To construct the solar thermal power stations in areas throughout central Australia will require large mobile construction camps, fly-in fly-out work force, large concrete batch plants, large supply of water, energy and good roads to each power station. Air fields suitable for fly-in fly-out will be required at say one per 250 MW power station. That means we need to build such air fields at the rate of about two, then three, then four per year.]. Solar thermal needs to be built in areas of high insolation (deserts) and the power stations must be widely distributed to minimise the impacts of widespread cloud cover.

5. Transmission costs are included at the rate of $1,200/kW (derived from estimates in AEMO, 2009).

Solar thermal capacity is commissioned at the rate of 0.5 GW per year from 2020 to 2025, then at 0.75 GW per year to 2030, then at 1 GW per year to 2050. However, from 2040, some of the new build is for replacing existing old capacity. Solar thermal capacity is assumed to have the same capacity factor as nuclear, i.e. 90%. This is based on NEEDS (2008) which forecasts that solar thermal will have this capability by 2020 [There is an alternative to solar thermal with sufficient energy storage for 90% capacity factor. The alternative is solar thermal hybrid. Gas generates power when the sun isn’t shining and there is insufficient energy storage. The hybrid options emits much more CO2 than CST alone and the electricity costs are higher (EPRI, 2009a, page 10-20), although this comparison is made at a capacity factor of 34% not 90%. NEEDS argues that the solar thermal with 8000 full load hours energy storage will be available and electricity costs will be less than the hybrid option by 2020. The hybrid option is not included in the options considered here].

CCGT is commissioned at the rate needed to make up the difference between the energy that the solar thermal capacity can provide and the energy deficit caused by decommissioning the coal fired power stations.

From 2010 to 2019, negligible solar thermal is commissioned so CCGT is built at the same rate as in Option 2 – CCGT and Option 3 – Nuclear & CCGT. From 2020 to 2040 CCGT is being added because solar thermal is not being built fast enough to replace the coal capacity being decommissioned. By 2040 all coal capacity has been decommissioned. So, from 2040 less energy is being required from CCGT. This shows up, in this simple analysis, as reduction in CCGT capacity. The practical interpretation of the reduction of CCGT capacity is that the Natural Gas generation capacity would be reduced at this rate. What this means is that the Natural Gas generation would not be replaced at the end of its 30 year economic life. This begins from about 2040. Figure 5 shows how much energy is produced by each technology.

CO2 emissions for solar thermal are assumed to be zero (refer Table 1). CO2 emissions for coal, CCGT and the other technologies are calculated in the same way as for Option 3 – Nuclear and CCGT. The negative emissions shown against CCGT should actually be a reduction in emissions from ‘Natural Gas’ but for simplicity they are shown as negative against CCGT.

The capital cost calculations for this option are similar to those for Option 3 – Nuclear and CCGT, except that the capital cost of transmission is added and the capital cost of replacing retiring solar thermal capacity is included from 2045. The capital cost of the solar thermal capacity is based on adjusted unit rates from NEEDS (2008), Figure 3.11, Case B [The ‘learning rates’, and hence the costs, in the NEEDS report seem optimistic (see Appendix 2)]. The rates are adjusted to attempt to make them more consistent with the way the ACIL-Tasman (2009) rates were derived. Two adjustments were made. Firstly, the initial capital cost unit rate is adjusted up by 25% to allow for the greater cost of constructing widely distributed power stations across an area roughly 1000 km by 3000 km of Australia’s deserts. Secondly, the learning rate in NEEDS (2008) is replaced with the same rate of cost reduction as for nuclear in Option 3- Nuclear and CCGT.

The capacity factor assumed for solar thermal is the same as for nuclear, coal and gas. This requires that the solar thermal power stations have sufficient energy storage for 24 hour operation and can provide for 8,000 full-load hours per year. Needs (2008) forecast that this capability could be available by 2020. The additional capacity needed to ensure full power generation throughout winter and throughout periods of overcast weather (Lang, 2009b), is not allowed for in this analysis.

As for wind, transmission is a significant cost item for solar thermal. The capital expenditure for transmission for solar thermal is calculated at $1200/kW (based on estimates in AEMO, 2009). Electricity cost includes $15/MWh for transmission.

Option 6 – Solar Thermal, Wind and Gas

For this option, it is assumed that solar thermal is commissioned at the same rate as in Option 5 – Solar Thermal & CCGT. Wind, CCGT and OCGT are commissioned at the same rate as in Option 4 – Wind & Gas. The solar capacity does not reduce the amount of gas capacity needed to back-up for the wind capacity. Gas capacity required to back up for wind does not change but the amount of energy the gas generates does change, with the gas generators working at lower capacity factors.

The energy generated by solar thermal is the same as in Option 5 – Solar Thermal and CCGT. The energy generated by wind is the same as in Option 4 – Wind & Gas. The energy generated by OCGT and CCGT makes up the energy deficit. Figure 6 shows how much energy is produced by each technology.

CO2 emissions for wind and solar are assumed to be zero in this analysis (see Table 1). CO2 emissions for OCGT, CCGT, coal and the other seven technologies are calculated in the same way as for Option 4 – Wind and Gas.

The capital cost calculations for this option are similar to those for Option 4 – Wind & Gas and Option 5 – Solar Thermal & CCGT. The capital cost of the solar capacity in this option is the same as for Option 5 – Solar Thermal & CCGT. The capital cost of the wind capacity is the same as for Option 4 – Wind & Gas. The capital cost of the gas capacity is less than Option 4 – Wind & Gas because of the contribution from solar thermal; solar thermal provides its share of energy and the gas makes up the deficit. Transmission cost is included at $15/MWh for solar thermal and for wind.

Build rates

The rate of decommissioning coal and commissioning the replacement generating capacity, for each option, is summarised in Table 3. The figures in the shaded cells are prescribed inputs and the unshaded cells are calculated values.

Electricity Costs

The cost of electricity, for coal and the replacement technologies, was calculated for each option. The electricity costs were calculated by applying the electricity cost unit rate (see Table 4 and Appendix 2) to the proportion of energy generated by each technology. Appendix 2 explains the sources and derivation of the electricity cost unit rates for use in this analysis.

CO2 Avoidance Cost

The CO2 avoidance cost (the cost to avoid a tonne of CO2 emissions) was calculated for each option. It is the difference in electricity cost between Business as Usual and the respective option divided by the difference in CO2 emission between the Business as Usual and the respective option.

Results

The results of the analyses are summarised in Figures 7 to 12.

Figure 7 compares the total CO2 emissions per year from the six options.

Figure 8 compares the capital expenditure per 5 years for the six options. The capital expenditure is for coal and the replacement technologies only. The capital expenditure for the other seven technologies is the same for all options; these costs are not included in the total capital expenditure figures shown here.

Figure 9 compares the cumulative capital expenditure of the six options.

Figure 10 shows the long run marginal cost of electricity for coal and the replacement technologies only. These costs do not include the cost for the seven technologies that are the same in all options.

Figure 11 compares the options on the basis of the CO2 avoidance cost; i.e. the cost to avoid a tonne of CO2.

Discussion

The following can be interpreted from Figures 7 and 8:

Option 1 – Business as Usual produces the highest CO2 emissions by a large margin. Capital expenditure is fairly consistent at about $10 to $15 billion per 5 years, or about $2 to $3 billion per year.

Option 2 – CCGT has the highest emissions of the replacement options. It has the lowest capital cost of all options (although it has the highest operating cost). The CO2 emissions with this option are only slightly less in 2050 than in 2010. The reason the curve turns up from 2040 is that all coal fired power stations have been decommissioned. Therefore, CCGT is being added but no coal is being removed. So we are adding emissions from the CCGT without cutting any from coal generation.

Option 3 – Nuclear and CCGT has the lowest CO2 emissions from 2020. It has the lowest capital expenditure, except Business as Usual and CCGT, for most of the period from 2010 to 2050. From 2035 the capital expenditure rate decreases.

Option 4 – Wind, with CCGT and OCGT for back-up, produces slightly lower CO2 emissions than the CCGT. However, this is achieved at high cost – about $4 billion to $6 billion per year more than CCGT. The step up in expenditure in 2040 is for replacement of the wind capacity installed in 2015. The emissions increase from 2040 as electricity demand increases and once the coal generators have been decommissioned.

Option 5 – Solar Thermal and CCGT. Solar thermal capacity is built at half the rate of nuclear, and provides half the energy. CCGT must be built faster in the solar option than in the nuclear option to make up the energy deficit. The CO2 emissions from 2010 to 2019 are the same for the three options CCGT, Nuclear & CCGT and Wind & CCGT. From 2020, the CO2 emissions from the solar thermal option are higher than from the nuclear option. By 2050, the CO2 emissions from the solar thermal option are over three times those from the nuclear option, and increasing as electricity demand increases. The capital expenditure for the solar option is substantially higher than for nuclear throughout.

Option 6 – Solar, Wind and Gas is a combination of Options 4 and 5. CO2 emissions are the second lowest from 2020 to 2050. Importantly, this option requires around $5 billion to $6 billion per year higher capital expenditure than nuclear to 2030. From 2030 to 2050 the difference in capital expenditure blows out to over $10 billion per year higher rate of expenditure for this option.

Figure 9 shows the cumulative capital cost and Figure 10 shows the long run marginal cost of electricity (LRMC). The following can be interpreted from these two charts:

CCGT is the lowest cost option throughout the period from 2010 to 2050.

Nuclear & CCGT has the lowest total cost (cumulative capital expenditure) of all options except Business as Usual and CCGT. The electricity cost for the Nuclear & CCGT option peaks in 2045 then starts to decrease as Natural Gas is decommissioned.

The steep rise in capital expenditure and electricity cost for the Wind option and the Solar Thermal and Wind option is because of the high cost of Wind and because Wind is being added at the rate of 1.4 GW per year from 2011, which is three times the rate Wind was commissioned in 2008.

The options with wind and solar thermal produce the highest cost electricity throughout.

The cumulative capital expenditure for the Solar Thermal option is about 30% higher than for nuclear. This is despite the fact that the solar thermal capacity is being built at half the rate of nuclear.

Important to note: The electricity cost for the Solar Thermal, Wind and Gas option is higher than the Solar Thermal and CCGT option. This indicates that combining renewable energy generators does not reduce the cost.

Figure 11 compares the options on the basis of the cost of avoiding a tonne of CO2 emissions. The CCGT option has the lowest avoidance cost to 2035 and then the Nuclear & CCGT option is lowest thereafter. The difference, in 2015, between the options that have Wind in their mix ($163/tCO2-e) and those that do not (50/tCO2-e) is because wind with gas back up is far more expensive but avoids insignificant extra emissions (see Figure 7). In the long run, Nuclear & CCGT is the least cost way to reduce emissions from electricity generation. The options with Wind and Solar are the highest cost way to avoid emissions.

How achievable are the assumed build rates?

The build rate for Business as Usual has been achieved consistently to date, so there can be no doubt that it is achievable.

The build rate for CCGT is about twice the build rate for coal in the Business as Usual case and about 15 times the current build rate for Natural Gas generation plant.

The build rate for wind capacity (1.4 GW per year) is about 3 times the build rate achieved in 2008 (0.48 GW) (GWEC, 2008). For comparison, in 2008 USA installed 8.4 GW and China 6.3 GW (GWEC, 2009). Interestingly, developed countries with larger economies than Australia, installed not much more than Australia, e.g. Canada (0.5 GW). AER (2009), Table 1.4 shows a peak for proposed commissioning of 2.8 GW in 2011. In practice, the build rate for wind will be limited by transmission capacity and the amount of wind power that can be accepted by the grid. The assumed build rate of 1.4 GW per year (500-700 turbines a year based on current turbine sizes) seems achievable in the future.

The rate of commissioning nuclear from 2020 to 2025 is 1 GW per year. That is equivalent to one new reactor per mainland state every 5 years. To put this in perspective, France commissioned its Gen II nuclear power plants at the rate of 3 GW per year for two decades (WNA, 2009). And Japan, China and Korea have been building the new Gen III nuclear power plants in about 4 years. So, it would seem the build rate for nuclear assumed here could be achieved from 2020, if necessary.

The assumed rate of commissioning solar thermal in these analyses, seems highly optimistic. The quantity of steel and concrete required is an indication of the amount of construction effort required. Solar thermal requires about 8 times more concrete and 15 times more steel than nuclear per MW of capacity (Table 5). The build rate for solar thermal, assumed in these analyses, is half the rate of nuclear, so each year we would need to construct solar thermal plants comprising 4 times more concrete and seven times more steel than the nuclear plants. But that’s not all. Nuclear would be built relatively close to the population centres, where services, infrastructure and work force is more readily available. Conversely, the solar plants need to be built in the desert regions. They will require four times as much water (for concrete) as nuclear. Water pipe lines will need to be built across the desert to supply the water. Dams will need to be built in the tropical north to store water and desalination plants along the coast elsewhere. To develop and retain a skilled work force to work in such regions will be costly. Work will be for about 9 months of the year to avoid the hottest periods. Based on the quantities of steel and concrete, towns will be required in the desert that accommodate about four times the work force required for constructing a nuclear power station. Fly-in-fly-out airports will need to be built for each town with a capability to move much larger numbers of people than the largest mining operations. Two such towns and airfields must be built per year to achieve the solar thermal build rate. It is hard to imagine how a build rate for solar thermal could be even 1/10th the build rate that could be achieved with nuclear.

The build rate for nuclear would be difficult to achieve. But the build rates for solar thermal would be much more difficult to achieve.

Sensitivity to assumptions and inputs

The results are highly sensitive to some of the assumptions and inputs. The most sensitive inputs are the projections of future capital cost, electricity cost, and the development rates for solar thermal. However, the ranking of the options under different inputs, and therefore the conclusions are robust over the ranges tested.

Answers to the questions

This paper set out to address the two questions stated in the Introduction, viz.:

1. Does it make sense to build wind power as fast as possible until 2020, at least, so we can cut greenhouse gas emissions as quickly as possible and start cutting as early as possible?

2. Would a mix of technologies be better able to meet the demand and do so at lower cost? For example, would a mix of solar and wind be lower cost than either alone, and lower cost than nuclear?

Figure 11 provides the answers.

The answer to Question 1 is ‘No’. Figure 11 shows the emissions avoidance cost for the options without wind is $50/tCO2-e and for the options with wind is $163/tCO2-e in 2015. In 2020, the ranking is the same but the costs are higher (see Figure 11).

The answer to Question 2 is ‘No’. The option with the mix of Solar Thermal and Wind has the highest avoidance cost of all options. It has the highest capital expenditure by far (Figures 8 and 9), and the highest electricity cost (figure 10). Its CO2 emissions are greater than the nuclear option. It has no advantages.

Figure 12 summarises the position in 2050. The figure compares the six options on the basis of the electricity cost of the coal and replacement technologies and the total CO2 emissions per year for each option. Clearly, the Nuclear and CCGT option produces the lowest emissions and the cost penalty is marginally higher than CCGT.

Conclusions

The Nuclear power option will enable the largest cut in CO2-e emissions from electricity generation.

The Nuclear option is the only option that can be built quickly enough to make the deep cuts required by 2050.

The Nuclear option is the least cost of the options that can cut emissions sustainably.

Wind and solar are the highest cost ways to cut emissions.

A mixture of solar thermal and wind power is the highest cost and has the highest avoidance cost of the options considered. Mixing these technologies does not reduce the cost, it increases the cost.

The results are sensitive to the input assumptions and input data, but the ranking of the options, and therefore the conclusions, are robust to the changes of inputs tested.

——————————————————————

For more information on assumptions and calculations, with references to source material, please read the 32-page PDF version.

Add to FacebookAdd to NewsvineAdd to DiggAdd to Del.icio.usAdd to StumbleuponAdd to RedditAdd to BlinklistAdd to TwitterAdd to TechnoratiAdd to Furl

By Barry Brook

Barry Brook is an ARC Laureate Fellow and Chair of Environmental Sustainability at the University of Tasmania. He researches global change, ecology and energy.

342 replies on “Emission cuts realities for electricity generation – costs and CO2 emissions”

BilB,

I refer you to John Morgan’s comment on 21 May 2010 at 9.22 where he asked you:

BilB, once again,

* what assumptions do you object to? What are your preferred alternative assumptions?
* What new techniques do you refer to? How do they alter the estimates?
* What lifetime do you think should be attributed to nuclear plants?
* What (definite, not indefinite) lifetime do you attribute to a capable CSP system?

Just throwing out unquantified, unargued statements like this is vacuous.

Like

BilB, Peter, why don’t we work through this systematically, it’ll be much easier for all of us. In that spirit, BilB, could you write a short comment outlining your highest priority critique of Lang’s work (e.g. most glaring assumption, unjustified calculation, whatever), and explain (briefly) why you consider it flawed. That way, Peter (and others) can respond, and we can work our way iteratively through your list of concerns. Otherwise, we’re not going to get anywhere.

Like

Barry,

That seems an excellent approach. We need a circuit breaker to this discussion as it is going nowhere.

Like

Good method, Barry. It will take me several days as my design load has piled up. I will read through Peter’s paper item by item and log where I believe divergent errors originate.

Like

This is good. Maybe, if time is an issue for you, just start with one item – the one you think is the single biggest factor.

Like

Joh M,

I am working on it, but here is a little taste of what to expect. The subject “state of the art” Qeanbeyan Solar Farm was installed in December 1998 with BP 77 watt panels. That should tell you something about efficiencies, pricing projections, energy conversion technology, and industry knowledge that was used in this study, and their relevence to making projections on solar energy outcomes into the future. There is one positive, and that is that a current day study might shed light on photovoltaic panel durability as these panels are half way through the oft sceptic claimed 20 year panel life.

Like

Thanks for that update BilB – we’ll look forward to reading it.

If you do object to the use of the Queanbeyan example, the question will then be, what parameters do you think fairly represent the state of the art of solar farm technology, and do they change the ultimate conclusion? Referring to an existing installation would be nice.

Like

From Kent Hawkins:

I just published a four-part series on MasterResource of the recently released studies on the Netherlands electricity system and the Bentek study for Colorado and Texas. Both studies show zero CO2 emissions (the Netherlands at 3% wind penetration) to increased CO2 (Colorado and Texas – both at 5-6% wind penetration). I compared the results to what my calculator predicted. Part I starts here http://www.masterresource.org/2010/05/wind-integration-realities-part-i/#more-9977 . Comments are appreciated.

The links to the following parts are broken so here is the link Part IV (you can get to the others from here): http://www.masterresource.org/2010/05/wind-integration-realities-texas-iv/#more-10008

This reports on preliminary analyses that appear to confirm the the outputs of the Kent Hawkins’ Calculator. That is, they show that the emissions from the fossil fuel back-up for wind power are similar to or exceed the emissions with no wind power in the system. In other words, Wind power is not reducing emissions. (But it is certainly raising the cost of electricity significantly).

Like

BilB, on 30 May 2010 at 12.32 Said:

“That is purely an anomaly based on missmatched and incomplete systems.”

That’s what we call hand waving BilB. You have to show where and how these calculations are in error.

Like

They are not in error, dv8, I would expect. They are the outcome of systems that are not tuned to operate harmoniously. Furthermore the parts of the system that do, by design, cooperate interactively are not installed. It is what you would call teething problems on a very large scale. There was a comment earlier about energy routing. Energy flow managers are only now coming to terms with the reality that energy flows in the future need to be bidirectional, rather than one way.

The inference that renewables do not reduce CO2 emissions is completely false. That poorly designed and coordinated energy systems can be less CO2 efficient is a more correct deduction.

Like

BilB, I have a strong sense of deja vu about your comment. I know I’m sounding like a broken record, but, can you please try to be specific in your comments, both in terms of your critique, and the alternative you would offer?

In this case, if you believe that wind power can be harmoniously integrated with gas backup, can you explain how your preferred system differs from our present one? How is wind harmoniously integrated with other generators? What exactly are you saying?

There is a genuine willingness here to discuss these issues. But without reducing these statements to concrete implementations, all we have to go on is your sense of “the vibe”.

I trust your promised critique of Peter’s analysis, and your geologist friend’s contribution, is coming along soon.

Like

@ John Morgan – the poster BilB, has nothing, nothing at all. That’s why the only think he can do is try and blow smoke in everyone’s eyes with nonsense like like his previous comment.

The two-way grid is the worst of these smoke screens. A commenter called Rich at Atomic Insights put it best:

There are two problems with distributed power systems that the idealists do not discuss assuming these distributed generators are big enough to feed back to the grid. One is the fact that the present power distribution system is designed to take power from a central source and spread it out to where it is used. It is NOT designed to do the reverse. The big feeder breakers and the fault overload timing sequence is designed to cut off the fault closest to the fault and keep everybody else with power. (That is why your main breaker does not trip when your saw binds up cutting a board and trips the breaker for the shop.) The protective circuitry is NOT there (for both equipment and personnel). To correct this problem will take a “genius grid,” a “smart grid” will not hack it. Each of these distributed generators will require protective circuits and controls with main dispatcher monitoring, control, and readout. Most existing substations would require an extensive overhaul, replacing all existing protective equipment with two-way protective circuits. Even then, IMHO reliability will decrease and power critical installations (e.g. hospitals, server farms, etc.) will get their own power and go off grid. The present control system is on the verge of overload now. This problem is not shown now because there are so few private generators feeding back on the grid.

Secondly, the efficiency of a generation system drops drastically as you decrease the load from the optimum load, typically 90 to 100% of design, think of highway vs. city MPG in a big semi. Sending power from two areas where there is only 30% load to another area where there is 30% load to get one generator at 90 to 100% load heats up a lot of wire (I square R losses), not to mention the efficiency losses for the period of time until you can combine loads. You then have travelling maintenance crews, distributed maintenance facilities, warehouses, etc., etc. Look at the recent proliferation of high efficiency CCGT units – each that I have seen has more than one unit. No NRC B/S, so one crew can operate and maintain both, three, possibly even four. Put four single units on the four corners of your city and union rules will dictate four crews or work rules that would bankrupt you. Are we trying to save GAS? Electricity? reduce CO2? or create jobs? The only thing I see happening is creating jobs.

Source: Here

Like

Most of what Rich has written there, Dv8 is hype and smoke spcreen. All except the breaker issue. That is real, and I’m going to have look into that very carefully. I suspect that the solution is in noise monitoring. By analysing the nature of the the waveform it should be possible to determine if a line segment has become isolated. These techniques are employed with phenomenal precision in motor control systems. Then again it might be as simple as monitoring line current imbalance, very simple.

Like

It’s not Hype BilB, it’s the truth, and I know it. The distribution problem is real and has been recognized by several in the renewable field as no yet solved. And the point about I square R losses, is simple physics.

Again, if you are going to mount a criticism of anyone’s statements, it has to be substantive; merely stating it’s hype without explanation, makes it look like you have no explanation to give. Every time you do this, you undermine your own credibility, far more than you damage that of you opponent. It is very clear to all of us here now, that you have nothing, and that you are incapable of mounting any sort of rational argument, supported by numbers, for your contentions.

I’m afraid you cannot be taken seriously, until you do.

Like

Dv8,

Rich points to the hysterical nature of his comments here

“This problem is not shown now because there are so few private generators feeding back on the grid”

where he says that there actually isn’t a problem, there just might be, oneday. Which rounds out as there being a known problem which when properly specified into new equipment entering the system will ensure that there never is a problem.

Dv8, it is you who cannot be taken seriously.

Like

Oh I’m detached all right. This poster has provided no facts, and no substantive logic to back his claims. He has made several transparently false attempts to style himself an expert, and then demands we accept what he says on that basis.

This is not the first time I have run across this sort of wannabe fraud on the net, nor will it be the last. It’s always the same – they can never back up their claims ever and will string it out as long as they can. The usual pattern is for them to push as far as they can, until a critical number of people, demand reference, or call them out, then they disappear in a cloud of insults, suggesting that they are throwing pearls among swine.

After awhile you can pick up on these types almost as soon as they first post.

Like

Getting to it, Dv8, but having read your background an philosophy I’m surprised that you haven’t picked the huge number of holes in Peter’s projected conclusions from his essay. I’ve got to wonder how thorough you were as a technician.

Like

Dv8 it is you who is flinging the insults around with gay abandon, so expect to eventually get some back. No libel there. Just a question. What sort of technician where you?

Like

BilB has been ‘getting around’ to a number of critical posts which contain the information and references needed to back up his points for well over a month now. He’s only managed to find time to throw around unsupported assertions so far, so we can only conclude that he is extraordinarily busy.

Or something.

Like

if someone considently adds absolutely nothing, other than libel, then can’t they just be banned? BilB back up your opinion with numbers, figures or facts. Otherwise go home.

Like

BilB is gone – this type fights until they are cornered with a demand for facts, and when they realize they cannot supply them, they first try and hijack the thread, then they vanish. If that person ever posts again here, it will be under another name.

Like

Gone but not forgotten. I’m confident that in a decade or so, the reality of what BilB and fellow-travellers were really fighting for will be well recognised in political and legal circles, and every effort will be made to track these people down so they don’t evade their overdue appointment with the gallows.

Like

I certainly wouldn’t want to see anyone banned on this basis. When posters like BilB demonstrably fail to substantiate their assertions, they make our case for us.

That said, I would really like to see BilB’s continued engagement with this discussion to some sort of closure, so if anyone encounters him in discussions elsewhere please remind him of his promises here, and drop a link here.

Like

I recall the thread on the John Quiggin blog (now in hiatus) in which the ‘baseload fallacy’ was taken as pre-condition for discussion. A certain commenter was given free rein while others were in effect censored. However one comment troubled me which was that European wind power had greatly increased while nuclear output had declined. It also grew faster in absolute terms than gas fired generation. Apart from retirement of nuclear plant I now believe the response should have been that European wind generators were made an offer too good to refuse.

To the best of my knowledge Euro wind gets multiple layers of help. On the one hand they get mandates or quotas i.e. guaranteed custom. That’s the ‘cake’. On top of that they get a thick layer of icing in the form of feed-in tariffs. If there was any way to integrate wind power into the mix it would be crazy not to take the money. I think that answers an open question from the Quiggin blog.

Like

The report indicated that 8x more concrete and 15x more steel is needed for construction of windpower per MW compared to nuclear. What the report failed to consider is the energy required to produce these materials and the hazardous wastes that are produced. My calculations indicate that more energy/MW over its life time is required for windpower compared to nuclear, thus resulting in a larger carbon footprint for windpower. This assumes centrifuge enrichment for nuclear fuel production. I assume this would be worst for solar since it requires more materials. Any life cycle analysis needs to include this consideration. There is no free lunch in energy production

Like

no relation to this Peter Lang who obviously hadn’t heard of the approach of Sweden, Finland, Poland, Austria, Denmark etc in using biomass (and municipal waste) to produce a significant amount of their energy when he wrote this book.

In the case of Sweden it is over 31% (already more than any other source including hydro or nuclear) heading for over 39% by 2020. Finland gets nearly 20% of its electricity from biomass and 50% of primary energy in central Finland,
Brazil is a high achiever, India is developing biomass-fuelled baseload off-grid mini-grid systems for 10,000 villages using biomass fuelled gasifiers. Overall India can get 10% of electricity from biomass plus a vast amount of domestic and industrial heat. China is building biomass fuelled power plants using straw.
But nothing about biomass in this book, or other books that portray themselves as authoritative, but have similar flaws in their initial approach.